Construction on Locsut Walk began this summer and was slated to be completed by Sept. 30. While work on the 3600 block was completed five days ahead of schedule on Aug. 26, construction on the 3800 and 3900 blocks suffered major delays due to heavy rains and damage to two storm sewers.